We are currently under contract for four projects worth a total of over $100M. We have a long history at Blue Plains and an excellent rapport with the DC Water and Sewer Authority.
![]()
Additional Dewatering Facility ($57M)
Owner: DC Water and Sewer Authority
Washington, DC
This project involves a large addition/retrofit of the Dewatering Facility. Included in the work is the construction of seven high performance dewatering centrifuges and two biosolids storage silos, as well as modifications to existing centrifuges.
Metal Salts and Additional Disinfection Facility ($48M)
Owner: DC Water and Sewer Authority
Washington, DC
We are currently constructing a new Chemical Receiving Station for metal salts, a new Chlorination Building for sodium hypochlorite, and a new Dechlorination Building for sodium bisulfate. We are also making several modifications to the existing Chemical Building.
Filtration Facility Pumping System Upgrade ($9M)
Owner: DC Water and Sewer Authority
Washington, DC
We are finishing up this project, which involves extensive improvements to the pumping system at the Filtration Facility. We are removing and replacing 45 pumps, including influent, effluent, washwater, and chlorine injector pumps.
Grit Removal Upgrades - East Process
($26.3M)
Owner: DC
Water and Sewer Authority
Washington,
DC
This project involves significant upgrades to the Grit Removal Facility. These
upgrades include grit processing equipment, mechanical, and electrical systems,
and architectural upgrades.